180 Cabrini
News and announcements for 180 Cabrini Blvd.
180 – Thermostatic Radiator Valve Installation
As announced in our memo of June 11th, Thermostatic Radiator Valves (TRVs) will be installed on all radiators in your apartment except those found in the bathrooms. A TRV is a self-regulating valve that replaces your existing manual radiator valve. It acts as a thermostat to control the temperature of a room. You need only set the TRV to your desired comfort level once and the self regulating valve automatically controls the flow of steam to that radiator. If you wish, the valve can also be shut off completely.
We expect to start installations in your building on Tuesday July 20th . The intention is to install at least 30 valves per day starting at the penthouse level and moving down the building three floors per day.
You must call the management office to advise if you will be home or how access to your apartment will be arranged. Evening and weekend appointments are also available.
Installations take about twenty minutes per valve.
Glashow Plumbing, a trusted and regularly used plumber at Castle Village, will be doing the installations. The workmen will be accompanied by Castle Village staff during the installation. If you have elected to have water saving showerheads and aerators installed, Castle Village staff will mount them while the plumbers are installing the TRVs.
The table below shows the schedule the contractor will try to follow. The schedule might change depending on the pace of the job. Keeping to the schedule also relies on your cooperation. Please make your apartment available on the days that correspond to your floor. If you cannot be home on the day allotted for your floor, installations can also be performed on weekends and after work hours by in-house staff.
DAY DATE FLOOR
Tuesday 20-Jul PH, 11 & 10
Wednesday 21-Jul 9, 8 & 7
Thursday 22-Jul 6, 5 & 4
Friday 23-Jul 3, 2, 1 & Sublevel
Precautions
• Please remove furniture and breakables from in front of, on and around the radiators.
• If there is heavy furniture that you have trouble moving, let us know in advance so staff can be prepared to help.
180 Exterior Masonry Work – 1 line
Starting Monday July 12th,, L&Z Building Restoration will be working along the 1 line master bedroom. The proposed work consists of demolition and reconstruction of brick at floors 12, 11, 10, 9, 5 and 6. You can expect loud noise due to the demo for at least 2 weeks. Work will start at 8:00am and [...]
180 Exterior Masonry Work – 7 & 8 lines
Starting Monday July 12th,, L&Z Building Restoration will be working along the 7-line bedroom and 8-line kitchen and small bedroom.Weather permitting the work will take approximately 5 weeks to complete. The proposed work consists of demolition and reconstruction of brick at floors 1, 3, 7, 8, and 11.You can expect loud noise due to the [...]
Building 180 – 1 & 9 Line Residents
Starting today July 1st, L&Z Building Restoration will be working along the 1 & 9-lines as indicated below. The work consists of caulking windows, brick demolition and reconstruction at several apartments along the drop shown. You can expect periods of loud noise due to the demo, which will start on July 6th and continue through [...]
Exterior work – 5 & 6 lines of Building 180
Starting Monday June 21st, L&Z Building Restoration will be working along the 5-line and 6-line as indicated below. The proposed work consists of demolition and reconstruction of brick at floors 11 and 12 but may progress to other areas if conditions warrant. You can expect loud noise due to the demo for at least 3-days [...]
Exterior Work – 7 & 8 Line Residents of Building 180
Starting Wednesday June 16th, L&Z Building Restoration will be working along the 8-line as indicated below. The work consists of demolition of brick from the 1st thru 3rd floors to repair a crack along the corner. You can expect loud noise due to the demo for at least 4-days followed by another week or so [...]
180 Masonry Work
Starting Tuesday June 1st, L&Z Building Restoration will start the next phase of exterior masonry work at your building on the 6 and 7-lines as indicated below. Weather permitting, the work will take approximately 5 weeks to complete. Periodic construction updates will advise on the progress and location of the work. There will be periods [...]
180 HOT WATER SHUT DOWN RESCHEDULED
The HOT WATER will be off from approximateley 9:00am to 3:00pm on Thursday, April 29th ,due to the need for plumbing repairs. In addition, please be advised that the Laundry Room will be closed during the above times. We regret any inconvenience and appreciate your understanding. Please be sure that all household faucets are securely [...]
180 Masonry Work
Starting Wednesday April 28th, L&Z Building Restoration will start mobilizing to start the next phase of exterior masonry work at your building by erecting sidewalk bridging over the front entrance and along the north side of the building. Scaffolding will be rigged from the roof along the lines where work is proposed. Exterior masonry work [...]
180 Submetering -Donut Installation
From Wednesday April 7th thru Friday April 9th, the submetering contractor will be installing the current measuring devices called donuts over the wires that feed your apartment. It is extremely important for billing purposes that the donuts be placed around the correct wires for each apartment. A survey of the electric panels shows that most [...]