Pleased to Announce The Arrival of Our New Gym

WE ARE PLEASED TO ANNOUNCE THE ARRIVAL OF OUR NEW GYM SCHEDULE (SUBJECT TO CHANGE AS ALWAYS) TUESDAY AUGUST 31 • NEW EQUIPMENT IS INSTALLED • A/C INSTALLATION IS FINISHED (HOPEFULLY) • ELECTRICIAN INSTALLS LIGHT SENSORS & FLOOR OUTLETS • FLOOR IS ALMOST FINISHED -SOME PARTS ARE ON BACK ORDER WEDNESDAY SEPTEMBER 1 • CABLE [...]

Residents of 120 – Cogen & Emergency Backup Installation

The Cogen and Emergency Backup Power installation that is part of the Energy Reduction Plan is nearing completion. All equipment is in place but final electrical tie-ins to building systems remain to be done. In order to do these connections safely, the power to the common areas and to the building systems must be shut [...]

Residents of 140 – Cogen & Emergency Backup Installation

The Cogen and Emergency Backup Power installation that is part of the Energy Reduction Plan is nearing completion. All equipment is in place but final electrical tie-ins to building systems remain to be done. In order to do these connections safely, the power to the common areas and to the building systems must be shut [...]

Residents of 160 – Cogen & Emergency Backup Installation

The Cogen and Emergency Backup Power installation that is part of the Energy Reduction Plan is nearing completion. All equipment is in place but final electrical tie-ins to building systems remain to be done. In order to do these connections safely, the power to the common areas and to the building systems must be shut [...]

Residents of 180 – Cogen & Emergency Backup Installation

The Cogen and Emergency Backup Power installation that is part of the Energy Reduction Plan is nearing completion. All equipment is in place but final electrical tie-ins to building systems remain to be done. In order to do these connections safely, the power to the common areas and to the building systems must be shut [...]

Residents of 200 – Cogen & Emergency Backup Installation

The Cogen and Emergency Backup Power installation that is part of the Energy Reduction Plan is nearing completion. All equipment is in place but final electrical tie-ins to building systems remain to be done. In order to do these connections safely, the power to the common areas and to the building systems must be shut [...]

Building 200 – 4 & 6 Line Residents

After months of delay due to permitting issues, L&Z Building Restoration will start mobilizing on Monday August 16th, to begin the next phase of exterior masonry work at your building. Exterior masonry work will commence on the 4 and 6-lines on Wednesday 8/18 and will progress southward around the building. The work is intended to [...]

200 Building Residents – Exterior Work

After months of delay due to permitting issues, L&Z Building Restoration will start mobilizing on Monday August 16th, to begin the next phase of exterior masonry work at your building. Exterior masonry work will commence on the 4 and 6-lines on Wednesday 8/18 and will progress southward around the building. The work is intended to [...]

180 & 200 Laundry Room Closing

The laundry room will be CLOSED most of the day on Monday, August 9th due to Con Edison working on the gas lines. We regret any inconvenience and thank you for your understanding.

140 & 160 Laundry Room Closing

The laundry room will be CLOSED most of the day on Friday, August 6th due to Con Edison working on the gas lines. We regret any inconvenience and thank you for your understanding.