Starting Wednesday June 16th, L&Z Building Restoration will be working along the 8-line as indicated below. The work consists of demolition of brick from the 1st thru 3rd floors to repair a crack along the corner. You can expect loud noise due to the demo for at least 4-days followed by another week or so of reconstruction.

Work will start at 8:00am and will close at 5:30pm Monday thru Friday. If necessary, quiet work will be allowed on Saturday.

Precautions/Procedures
• Keep your windows closed to avoid dust and debris from entering.
• Air conditioners will be protected with a filter fabric but it is best to avoid using them during the demolition if possible.
• In some cases, an air conditioner will have to be removed to properly perform the work required.
• To avoid possible damage to window and adjoining wall decorations, remove breakable items from these areas.
• Because of the bonded wall construction of our buildings, damage to interior surfaces of your apartment may occur during demolition. Any damage to the interior will be repaired.

We apologize for any inconvenience this may cause but the work is necessary to preserve the integrity of your building.